Free PMP Exam Practice Test 61 Questions And Solutions

Hi PMP aspirants, welcome to AKVTutorials. Ready to test your knowledge and skills with a diverse set of PMP Project Management Professional practice questions? Dive into PMP success with our Practice Questions—a strategic blend of challenge and insight for Project Management Professional aspirants. In this article, you will get Free PMP Exam Practice Test 61 Questions And Solutions. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

On a project to launch a satellite that will explore and provide data about black holes, the team spends time documenting how scope will be defined and controlled. What is a tool or technique that may be needed to perform this process?

Option A : Voting

Option B : Benchmarking 

Option C : Meetings 

Option D : Decomposition

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Meetings 

PMP Mock Test Question No 2

When considering adaptive projects, which of the following is not true?

Option A : If the project has high variability, a team with generalized specialists would be ideal 

Option B : Project artifacts should not be broadly shared among stakeholders 

Option C : Lightweight estimates are often used for a fast, high-level forecast 

Option D : Detailed estimates are provided in a “just-in-time” fashion

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Project artifacts should not be broadly shared among stakeholders 

PMP Practice Exam Question No 3

A project manager is working with a team to cleanup a hazardous waste site. During the project, she will need to work with several different parties that will be affected the project, including government officials and the local community, to ensure the project is successful. Which document outlines strategies for promoting the productive involvement of these parties?

Option A : Communication Styles Assessment 

Option B : Stakeholder Register 

Option C : Stakeholder Engagement Plan 

Option D : Communications Management Plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Stakeholder Engagement Plan 

PMP Mock Exam Question No 4

A project manager is preparing a resource management plan for a project that includes building a new military training complex. Which of the following would not be included in that document?

Option A : An explanation of how the team will ensure adequate physical resources are available 

Option B : A project organizational chart that shows reporting relationships for various team members

Option C : A description of how resources will be identified and acquired 

Option D : An explanation of values, agreements, and operating guidelines for the team

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

An explanation of values, agreements, and operating guidelines for the team

Project Management Professional Question No 5

You are currently meeting with several qualified vendors, who may provide products or services needed to complete the project work, prior to their submission of proposals. It provides them an opportunity to ask questions about what is needed. This scenario reflects which of the following processes?

Option A : Conduct Procurements 

Option B : Plan Procurement Management

Option C : Control Procurements 

Option D : Plan Stakeholder Engagement

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Conduct Procurements 

PMP Certification Prep Question No 6

Which of the following is not true about risk management on agile projects?

Option A : Risk and uncertainty is higher than on waterfall projects. 

Option B : Risk is managed through frequent reviews of incremental work products. 

Option C : Risk is identified, analyzed, and managed primarily at the beginning of the project. 

Option D : Throughout the project, requirements may be reprioritized as risks are better understood.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Risk is identified, analyzed, and managed primarily at the beginning of the project. 

PMP Exam Question No 7

On a construction project, you must get a permit from the local government before you start construction. This best describes which of the following dependencies?

Option A : Common 

Option B : Discretionary 

Option C : Internal 

Option D : External

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

External

PMP Exam Sample Question No 8

A project to decommission a naval base that has been left in disrepair has been funded and approved. However, the project manager has determined that they will need help from outside vendors to complete it. At this time, the scope is clearly defined, and the project manager does not expect any significant changes. The project is expected to span 10 years. In this scenario, which type of contract should be utilized?

Option A : Firm Fixed Price (FFP) 

Option B : Fixed Price Incentive Fee (FPIF) 

Option C : Fixed Price with Economic Price Adjustment (FP-EPA)

Option D : Cost Plus Award Fee (CPAF)

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Fixed Price with Economic Price Adjustment (FP-EPA)

PMP Exam Practice Question No 9

Your project team has been tasked with developing an e-commerce website. At this time, the team is planning risk responses. In doing so, which of the following activities might they perform?

Option A : Conducting root cause analysis to pinpoint the source of a problem.

Option B : Taking action to increase the likelihood that opportunities on the project occur. 

Option C : Determining if new risks have surfaced on the project — beyond those originally identified. 

Option D : Determining which risks to transfer to a third party.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Determining which risks to transfer to a third party

PMP Certification Exam Question No 10

An aerospace company that sends small satellites into orbit has several projects that are funded by government customers. Prior to the start of those projects, the company had to show that they were compliant with several government standards. In this scenario, these marketplace conditions would be best classified as which of the following?

Option A : An organizational process asset 

Option B : A procurement statement of work 

Option C : An enterprise environmental factor 

Option D : A marketplace condition

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

An organizational process asset 

PMP Latest Edition Mock Test Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply