PMP Exam Question Examples Test Paper 103

Hi PMP aspirants, welcome to AKVTutorials. Ready to take your PMP exam preparation to the next level with a comprehensive set of practice questions? Propel your PMP success story forward with our Practice Questions—a roadmap to conquering the Project Management Professional exam. In this article, you will get PMP Exam Prep Test 103 Questions Answers Explanations. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.

PMP Exam Practice Questions

PMP Exam Prep Practice Test Question No 1

A contingency plan___________.

Option A : identifies alternative strategies to be used to ensure project success if a specified risk event occurs.

Option B : is a work around.

Option C : is part of the management reserve

Option D : is the same as a fallback plan.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

identifies alternative strategies to be used to ensure project success if a specified risk event occurs.

PMP Exam Preparation Test Question No 2

All of the following are examples of theory X assumptions with the exception of:

Option A : employees avoid work.

Option B : employees need constant direction.

Option C : employees are self-directed.

Option D : employees are self-centered.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

employees are self-directed.

PMP Exam Sample Exam Question No 3

You have determined the duration for your project is 18.5 months with a standard deviation of 1.2 months. What technique will u use to determine the confidence level and the probability of completing the project on a specific day ?

Option A : PERT formula.

Option B : Monte carlo simulation.

Option C : Probability analysis.

Option D : Variance analysis.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Monte carlo simulation.

PMP Certification Exam Question No 4

Caltural noise in the communication channel can be caused by all of the following except?

Option A : Ethnocentric

Option B : Stereotyping.

Option C : Decorum.

Option D : Proximity distance between people

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Proximity distance between people

Free PMP Practice Exam Question No 5

 If PV $ 24000 and AC is $27000 and EV is 25000 we can report the project as follow:

Option A : Ahead of schedule and over budget .

Option B : Ahead of schedule and behind budget.

Option C : Behind schedule and over budget.

Option D : Behind schedule and under budget.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Ahead of schedule and over budget .

Best PMP Exam Practice Question No 6

 “For Consideration” in contract management means:

Option A : money must be paid from one party to another.

Option B : the contract must be signed.

Option C : the contract must be agreed to buy both parties.

Option D : there must be an exchange of things.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

there must be an exchange of things.

Free PMP Exam Prep Question No 7

The contemporary view of conflict is that :

Option A : conflict is bad.

Option B : conflict is caused by trouble maker.

Option C : conflict should be avoided.

Option D : conflict is often beneficial.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

conflict is often beneficial.

Latest PMP Exam Question No 8

A cost base line is an output of the _____________ management process.

Option A : Resource planning

Option B : Cost estimating

Option C : Cost budgeting

Option D : Cost control

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Cost budgeting

PMI PMP Exam Practice Question No 9

There are a variety of methods to select a projects. Which of the following is not a project selection criteria method.

Option A : Benefit measurement.

Option B : NPVA

Option C : The number of resources required to complete the project. 

Option D : Value analysis.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Value analysis.

PMP Certification Exam Agile Question No 10

Who originates the project charter ?

Option A : The project manager.

Option B : The project spencer

Option C : The client

Option D : A manager external to the project.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

A manager external to the project.

PMP Project Management Professional Practice Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply