PMP Latest Edition Exam Questions Mock Test 19

Hi PMP aspirants, welcome to AKVTutorials. Are you preparing for the PMP exam and looking for a resource that provides insightful practice questions for effective study sessions? Fast-track your PMP success with our Practice Questions—a comprehensive guide to mastering Project Management Professional concepts. In this article, you will get PMP Latest Edition Exam Questions Mock Test 19. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

During a project team meeting, a team member suggests an enhancement that falls outside of the project charter. The project manager states that the team needs to concentrate on completing all required work. Which action has the project manager performed?

Option A : Scope management

Option B : Conflict resolution

Option C : Scope creep

Option D : Change management

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Scope management

PMP Mock Test Question No 2

During the execution of a project with a limited budget, some of the team members suggest saving money by skipping quality management. What should the project manager do?

Option A : Accept the team’s suggestion due to the limited budget.

Option B : Ask the stakeholder to change the quality standards.

Option C : Ask the sponsor to increase the budget.

Option D : Educate the team on the importance of quality management.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Educate the team on the importance of quality management.

PMP Practice Exam Question No 3

A customer asks the project manager to deliver a project in 60 days that was previously scheduled for delivery in 90 days. No activities can be performed in parallel. The requested change is approved by the change control board (CCB).What should the project manager do to fulfill this request?

Option A : Fast track the project schedule.

Option B : Crash the project schedule.

Option C : Create a contingency reserve for the project schedule.

Option D : Create phases in the project schedule.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Crash the project schedule.

PMP Mock Exam Question No 4

A project manager is planning a project that has 40 stakeholders. The project manager decides that all stakeholders will receive the same type of communications in order to minimize work for the project team and reduce costs. When the project manager reviews the communications management plan with the project management team, experienced team member voices concerns about the communications decision. Why might using the same type of communication for all 40 stakeholders be a concern?

Option A : Because the team should be able to manage individual communications properly.

Option B : Because the expected savings would be minimal.

Option C : Because different stakeholder needs are not being taken into consideration.

Option D : Because some stakeholders might feel neglected.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Because different stakeholder needs are not being taken into consideration.

Project Management Professional Question No 5

A scope change requested by the customer was approved in accordance with the change management plan. The project team believes that the change contradicts the initial requirements and are resistant to it. What should the project manager do next?

Option A : Discuss the situation with the customer, and clarify the need for the change.

Option B : Proceed with the change, as it was approved in accordance with the change management plan.

Option C : Identify the resistant team members, and engage their functional managers.

Option D : Invite the customer to a team meeting to explain the need for the change.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Proceed with the change, as it was approved in accordance with the change management plan.

PMP Certification Prep Question No 6

Some project team members claim that they failed to receive complete project information. What should the project manager do to ensure proper information flow?

Option A : Initiate a weekly email newsletter.

Option B : Schedule a team meeting.

Option C : Follow the communications management plan.

Option D : Store information in a central database.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Store information in a central database.

PMP Exam Question No 7

During a demonstration, the customer provides feedback and requests a new, urgent enhancement due to a regulation change. What should the agile project manager do next?

Option A : Review the new requirement with the team, and ask them to start work on it.

Option B : Talk about the new requirement during the next iteration planning meeting.

Option C : Discuss the new requirement during the retrospective.

Option D : Add the new requirement to the iteration backlog

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Talk about the new requirement during the next iteration planning meeting.

PMP Exam Sample Question No 8

A project manager used geographically specific terms on a global project. Several stakeholders have rejected the plan due to their limited understanding of the terminology. What should the project manager do next?

Option A : Use an online translation tool to translate the plan into the various stakeholders’ languages and redistribute.

Option B : Ask stakeholders who rejected the plan to use a professional translator to help them understand it.

Option C : Discuss the terminology issues with stakeholders and add a glossary to the plan for future reference.

Option D : Revise the terminology to be more generic so the plan can be universally understood and agreed upon by all stakeholders.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Discuss the terminology issues with stakeholders and add a glossary to the plan for future reference.

PMP Exam Practice Question No 9

A development manager and project manager are reviewing the backlog for the next development sprint. Several of the user stories are incomplete, and the business analyst must update the user stories. While the user stories are being updated, the product owner requests features that were not previously identified. What should the project manager do next?

Option A : Update the backlog to include the additional features.

Option B : Submit a change request to the change control board (CCB).

Option C : Review the project scope statement for these features.

Option D : Acquire additional resources from the development manager.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Update the backlog to include the additional features

PMP Certification Exam Question No 10

A member of senior management informs the project manager that some of the features they thought were going to be delivered were not included in the current iteration. What should the project manager do?

Option A : Discuss the issue with the team, then advise the member of senior management on the status?

Option B : Meet with the stakeholders that requested the features to ensure that they are still valid requirements.

Option C : Tell the member of senior management that the features will be included in the next iteration.

Option D : Invite the member of senior management to the next iteration review meeting

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Invite the member of senior management to the next iteration review meeting

Free PMP Exam Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply