PMP Online Exam Questions Test 89 Paper

Hi PMP aspirants, welcome to AKVTutorials. Looking for practice questions that cover the principles of change management, a critical aspect of effective Project Management Professional practice? Ensure project quality with our PMP practice questions, delving into quality management principles for a robust Project Management Professional certification. In this article, you will get PMP Online Exam Questions Test 89 Paper. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

You are reviewing several feasibility reports. One report shows a benefit cost ratio of 2.1.This means:

Option A : The costs are 2.1 times the benefits.

Option B : The profit is 2.1 times the costs

Option C : The payback is 2.1 times the costs.

Option D : The cost is 2.1 times the profit.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

The payback is 2.1 times the costs.

PMP Mock Test Question No 2

A project has payback period of 1 and a half of years. What does that mean?

Option A : It will take the project one and half years before they start to incur costs.

Option B : The project will be completed in less than 2 years.

Option C : The company will receive the profits for the first one and half years of the project.

Option D : It will take the project one and half years to cover the investment and start generating revenue.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

It will take the project one and half years to cover the investment and start generating revenue.

PMP Practice Exam Question No 3

Your technical team leader who you highly respect has identified a design error that will mostly likely interfere with the meeting documented technical performance objectives. The best action to take is to:

Option A : Decrease the performance value to equal the assessed value.

Option B : Reduce the overall technical complexity of the project.

Option C : Increase the specified value to set a new performance goal.

Option D : Develop alternative solutions to the problem.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Develop alternative solutions to the problem.

PMP Mock Exam Question No 4

You are currently working for York Automobile, a market leader in manufacturing cars. Due to a shortage in petroleum based fuel as well as advent of new technology, the company has decided to venture into producing electrically powered cars. This project will be initiated due to a:

Option A : Market demand

Option B : Business need

Option C : Technological advancement

Option D : Social need.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Market demand

Project Management Professional Question No 5

First thing Tuesday morning ,one of your team member drops into your office looking very thrilled. He eagerly tells you he is adding extra functionality to the project without imparting the cost the schedule. As the project manager your first step should be:

Option A : Understand what the new functionality will add to the project and then action accordingly.

Option B : Implement change control processes to track the change.

Option C : Inform the customer of the change to the scope.

Option D : Notify the functional manager that scope changes are not approved.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Understand what the new functionality will add to the project and then action accordingly.

PMP Certification Prep Question No 6

Linear programming is an example of what type of project selection criterion?

Option A : Constrained optimization.

Option B : Comparative approach.

Option C : Benefit measurement.

Option D : Simulation.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Constrained optimization.

PMP Exam Question No 7

The “rolling wave” or “moving window” advocates the use of WBS decomposition and is used most frequently in the _____________ process.

Option A : Scope verification.

Option B : Scope planning.

Option C : Scope definition

Option D : Scope reporting

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Scope definition

PMP Exam Sample Question No 8

 The engineering department has flagged a concern about the expensive interface cards recommended to purchase for your switch cutover project. They believe they can find a less expensive but acceptable card and submit a `change request to do necessary research.

Option A : Input from a contractor that can supply the same interface card at a cheaper price.

Option B : An error or omission in defining the scope of the product.

Option C : An error or omission in defining the scope of the project.

Option D : a value-adding change.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

a value-adding change.

PMP Exam Practice Question No 9

You are conducting a product analysis in scope planning by prioritizing spoken and unspoken customer wows, wants and needs; translating these needs into technical characteristics and specification to build and deliver a quality product or service by focusing everybody toward customer satisfaction. This process is called :

Option A : Analysis system engineering .

Option B : Value engineering.

Option C : Quality function development.

Option D : Function analysis.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Quality function development.

PMP Certification Exam Question No 10

Out puts from the initiation process includes:

Option A : project manager assigned ,project character, and product description.

Option B : constraints, assumptions, and product description.

Option C : Project character ,Constraints, and assumptions

Option D : scope statement, project manager identified, and product description

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Project character ,Constraints, and assumptions

PMP Exam Practice Mock Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply