Sample Test 40 Exam Questions PMP Project Management Professional PMP

Hi PMP aspirants, welcome to AKVTutorials. Are you preparing for the PMP exam and in search of practice questions that emphasize the importance of continuous improvement and lessons learned? Leverage continuous improvement strategies with our PMP practice questions, ensuring your readiness for evolving project management scenarios. In this article, you will get Sample Test 40 Exam Questions PMP Project Management Professional PMP. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Which is not a type of project review meeting?

Option A : Team review meetings

Option B : Project status meetings

Option C : Executive management review meetings

Option D : Customer review meetings

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Project status meetings

PMP Mock Test Question No 2

You are performing integrated change control. Which of the following will not be part of what you do?

Option A : Reviewing and approving change requests

Option B : Maintaining the integrity of baselines

Option C : Performing milestone trend analysis (MTA) 

Option D : Documenting the allover impact of requested changes

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Performing milestone trend analysis (MTA)

PMP Practice Exam Question No 3

You are project manager for a strategic project with a multi-million dollars value assigned by a company that is listed at a US stock exchange. Recent Earned Value Analysis after app. 25% completion told you that your project has a CPI of 0.76. What should you do right now?

Option A : The variance is a signal of a sound project which is well under budget. There is no need for action. 

Option B : A project that much under budget may be a problem for negotiating future budgets. Try to spend money somewhere else. 

Option C : You should immediately inform your management, which should then assess whether this CPI constitutes a material financial issue..

Option D : It is still early in the project and data are yet inaccurate. Wait a while and allow numbers from the project to stabilize.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

You should immediately inform your management, which should then assess whether this CPI constitutes a material financial issue.

PMP Mock Exam Question No 4

A management point in a work breakdown structure (WBS) used to consolidate and process work package data and forward the results to the project manager is called

Option A : Control account 

Option B : Chart of accounts 

Option C : Control limit 

Option D : Account limit

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Control account 

Project Management Professional Question No 5

You are the project manager supervising several Scrum teams that work concurrently in your project. While you are planning the work items for your team members for the next three-months sprint, which criticism is should you expect your team to come up with?

Option A : Team members cannot begin to work on a specific activity without a permission written by the project manager. 

Option B : Terms such as “supervising” and “assigning” are inappropriate for the application of Scrum, where the team is self-managing.

Option C : A Sprint duration should be limited to 1 month or less to avoid that the Sprint goal becomes invalid. 

Option D : The project sponsor should first allocate team members to the project before the project manager can assign them to tasks. 

Option E : A Scrum project cannot consist of several teams working concurrently.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B, C 

Terms such as “supervising” and “assigning” are inappropriate for the application of Scrum, where the team is self-managing, A Sprint duration should be limited to 1 month or less to avoid that the Sprint goal becomes invalid. 

PMP Certification Prep Question No 6

When you perform quality assurance in your project, which technique could you typically use?

Option A : Code review

Option B : Quality audit 

Option C : Inspection 

Option D : Scope verification

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Quality audit 

PMP Exam Question No 7

The _______ can be used to assess outlays and funding requirements.

Option A : Cost assignment matrix 

Option B : Cost baseline 

Option C : Cost variance analysis

Option D : Control account plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Cost baseline 

PMP Exam Sample Question No 8

Which technique has been applied to develop the following diagram? 

Option A : Decision tree 

Option B : P/I matrix 

Option C : Strategic scoring 

Option D : Risk breakdown structure

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Decision tree 

PMP Exam Practice Question No 9

Your organization has the choice between several internal projects it could run. In order to select projects, the organization assessed their strategic importance, investment requirements, and expected cash inflow from the projects’ products, services and results. What should the organization assess in addition?

Option A : The probability of changes to strategic goals. 

Option B : The frequency of changes to strategic goals.

Option C : The assessments done should be sufficient. 

Option D : The probability of the expected cash inflows.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

The probability of the expected cash inflows.

PMP Certification Exam Question No 10

Which of the following is not a forecasting method?

Option A : Scenario building 

Option B : Simulation 

Option C : Time series method

Option D : Variance analysis

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Variance analysis

PMP Exam Practice Mock Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply