PMP Exam Practice Test 25 Questions Answer Keys

Hi PMP aspirants, welcome to AKVTutorials. Seeking a reliable platform for PMP practice questions that focus on risk management, a critical aspect of Project Management Professional certification? Secure your PMP success by mastering risk management with our practice questions, focusing on this critical aspect of Project Management Professional certification. In this article, you will get PMP Exam Practice Test 25 Questions Answer Keys. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

To control the schedule, a project manager is reanalyzing the project to predict project duration. She does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?

Option A : Critical path method

Option B : Flowchart

Option C : Precedence diagramming

Option D : Work breakdown structure

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Critical path method

PMP Mock Test Question No 2

A project manager has assembled the project team, identified 56 risks on the project, determined what would trigger the risks, rated them on a risk rating matrix, tested their assumptions and assessed the quality of the data used. The team is continuing to move through the risk management process. What has the project manager forgotten to do?

Option A : Simulation

Option B : Risk mitigation

Option C : Overall risk ranking for the project

Option D : Involving of other stakeholders

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Involving of other stakeholders

PMP Practice Exam Question No 3

Configuration management plan is:

Option A : Used to ensure that the description of the project product is correct and complete.

Option B : The creation of the work breakdown structure.

Option C : The set of procedures developed to control changes.

Option D : A mechanism to track budget and schedule variances.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

The set of procedures developed to control changes.

PMP Mock Exam Question No 4

A rough order of magnitude estimate is made during which project management process group?

Option A : Project planning

Option B : Project closing

Option C : Project executing

Option D : Project initiating

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Project initiating

Project Management Professional Question No 5

The work defined at the lowest level of the breakdown structure to estimate as well as manage time and cost is called the:

Option A : Activity

Option B : Task

Option C : Work package

Option D : Cost account

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Work package

PMP Certification Prep Question No 6

A project manager is working on an assessment project with a tight timeline. What should the project manager do first?

Option A : Develop a data-capturing system.

Option B : Look for lessons learned from previous, similar projects

Option C : Create a questionnaire for assessor proposals.

Option D : Appoint assessors and resources.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Look for lessons learned from previous, similar projects

PMP Exam Question No 7

All of the following are examples of the cost of nonconformance EXCEPT?

Option A : Rework

Option B : Quality training

Option C : Scrap

Option D : Warranty costs

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Quality training

PMP Exam Sample Question No 8

What type of contract do you not want to use if you do not have enough labor to audit invoices?

Option A : Cost plus fixed fee CPFF

Option B : Time & material T&M

Option C : Fixed price FPC

Option D : Fixed price incentive fee FPIF

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Cost plus fixed fee CPFF

PMP Exam Practice Question No 9

A project manager has just been assigned to a project. The document that recognizes the existence of the project is called:

Option A : The statement of work

Option B : The project assignment.

Option C : The project charter

Option D : The product description.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

The project charter.

PMP Certification Exam Question No 10

The WBS for the project represents:

Option A : All the tangible items that must be delivered to the client.

Option B : All the work that must be completed for the project.

Option C : The work that must be performed by the project team.

Option D : All the activities of the project.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

All the work that must be completed for the project.

PMP Practice Exam Questions Bank with Answers Keys

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply