Sample PMP Exam Questions Paper 108 Answer Keys Explanation

Hi PMP aspirants, welcome to AKVTutorials. Ready to challenge yourself with PMP practice questions designed to mirror the actual Project Management Professional exam? Seamlessly integrate PMP success into your journey using our Practice Questions—a must-have resource for Project Management Professional excellence. In this article, you will get Sample PMP Exam Questions Paper 108 Answer Keys Explanation. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.

PMP Exam Practice Questions

PMP Exam Prep Practice Test Question No 1

The quality team for the project consists of several groups. Which of the following project participant plays the most important role in the quality function?

Option A : Customer .

Option B : Project manager.

Option C : Project team.

Option D : Vendors and supplier.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Customer .

PMP Exam Preparation Test Question No 2

Earned value can best be defined as:

Option A : BCWP time ACWP. 

Option B : A method of ensuring project performance.

Option C : A method of tracking project costs.

Option D : SPI/CPI Units of production.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

A method of ensuring project performance.

PMP Exam Sample Exam Question No 3

Resource planning results in a description of what type of resources are required in what quantities. This plan is then used to support the subsequent process.

Option A : of cost estimating or budgeting.

Option B : of scheduling or controlling.

Option C : of staff acquisition and/or procurement.

Option D : of plan execution or cost controlling.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

 of staff acquisition and/or procurement.

PMP Certification Exam Question No 4

As project manager for a new communication project ,you received a PM services proposal which includes curriculum vitae for someone whom you have some knowledge of. This CV indicates that the individual has a PMP although you know that it is not true. Do you :

Option A : advise your superior of the false information.

Option B : advise PMI of the false information.

Option C : advise the individual of the mistake in the CV

Option D : A and B

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

 advise the individual of the mistake in the CV.

Free PMP Practice Exam Question No 5

Generally speaking the detail and frequency of performance speaking increases:

Option A : For executive management.

Option B : When risk increases

Option C : With contractors.

Option D : With team members.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

With team members.

Best PMP Exam Practice Question No 6

Destructive team roles includes which of the following?

Option A : Topic jumper, Devil’s advocate and information seeker.

Option B : Dominator, Recognition seeker and initiator.

Option C : Withdrawer Initiator and Aggressor.

Option D : Withdrawer ,Topic jumper and recognition seeker

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Dominator, Recognition seeker and initiator.

Free PMP Exam Prep Question No 7

An advantage of decentralized contracting is

Option A : The contract is a appropriate to project.

Option B : B. The contract follows appropriate guideline.

Option C : More focus on the contracts, therefore less mistakes.

Option D : The project manager has more control.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

 The project manager has more control.

Latest PMP Exam Question No 8

What is the Seller’s risk objective in Project procurement Management?

Option A : to get the highest dollar value contracts.

Option B : to minimize risk while maximizing profit potential.

Option C : to maximize risk so that profits are higher.

Option D : to minimize risk

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

 to minimize risk

PMI PMP Exam Practice Question No 9

When communicating the sender is responsible for:

Option A : Scheduling communicating exchange.

Option B : Ensuring the receiver agrees with the message.

Option C : Confirming message is understood.

Option D : Presenting the message in the most favorable manner

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Ensuring the receiver agrees with the message.

PMP Certification Exam Agile Question No 10

A firm fixed contract is one that is:

Option A : The firm is guaranteeing a fixed price.

Option B : The contract is fixed by the government authority

Option C : A lump-sum contract under which the seller furnishes goods or service at a fixed price.

Option D : The price of the Seller’s services are fixed on an hourly basis.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

A lump-sum contract under which the seller furnishes goods or service at a fixed price.

Best PMP Exam Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply