PMBOK PMP Exam Questions Practice Test 121 Answer Explanation

Hi PMP aspirants, welcome to AKVTutorials. Are you actively seeking PMP practice questions to simulate the exam environment and enhance your time management skills? Propel yourself toward PMP success by practicing with our updated questions, aligning with the latest changes in the Project Management Professional exam content. In this article, you will get PMBOK PMP Exam Questions Practice Test 121 Answer Explanation. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.

PMP Exam Practice Questions

PMP Exam Prep Practice Test Question No 1

Which of the following statements is not true?

Option A : Attribute sampling is the process of assessing whether results conform to specifications or not.

Option B : Prevention means keeping errors out of the process

Option C : Variables sampling means that the result is classified into one of the 3 categories: “acceptable” – “acceptable after rework” – “rejected”.

Option D : Inspection means keeping errors out of the hands of the customer

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Prevention means keeping errors out of the process

PMP Exam Preparation Test Question No 2

Why should assumptions be documented?

Option A : Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows baseline adjustments in case of project crisis.

Option B : Assumption analysis is a valuable tool and technique of Risk Identification.

Option C : Assumptions limit the project management team’s options for decision making.

Option D : In case of schedule or budget overruns, the documentation of assumptions supports a clear assignment of responsibility.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Assumptions limit the project management team’s options for decision making.

PMP Exam Sample Exam Question No 3

All the following statements are true except :

Option A : It is axiomatic of the quality management discipline that the benefits outweigh the costs.

Option B : Quality should be tested and inspected into work results on a regular base.

Option C : The primary cost of meeting quality requirements is the expense associated with project quality management activities.

Option D : The primary benefit of meeting quality requirements is less rework, which means higher productivity, lower costs, and increased stakeholder satisfaction.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Quality should be tested and inspected into work results on a regular base.

PMP Certification Exam Question No 4

Which of the following statements about diagramming methods is not true?

Option A : PDM is the same as AON.

Option B : ADM is the same as AOA.

Option C : GERT is the same as System Dynamics Model.

Option D : GERT and System Dynamic Model are examples of conditional diagramming methods.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

PDM is the same as AON.

Free PMP Practice Exam Question No 5

A project is managed by a project coordinator. Which of the following statements is most likely to be true?

Option A : The performing organization is a weak matrix.

Option B : The performing organization is doing “management by projects”

Option C : The performing organization is a strong matrix.

Option D : The performing organization is projectized.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

The performing organization is a strong matrix.

Best PMP Exam Practice Question No 6

 Which of the following statements concerning cross-cultural differences is true?

Option A : There is no one “best way” for project organization.

Option B : Some cultures have values, some not.

Option C : Cultural dilemmas should be denied to not allow them to disrupt project work.

Option D : Communicating across cultures should only be done using language. The nonverbal dimension bears too many risks.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

There is no one “best way” for project organization. 

Free PMP Exam Prep Question No 7

What are dummy activities?

Option A : Activities in PDM which are not necessary and can be dropped if time is running out

Option B : Arrows in ADM which represent dependencies between nodes without real activities.

Option C : Activities, which can be passed to the team members with the lowest IQ

Option D : Activities in PDM which are not performed by team members.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Activities in PDM which are not necessary and can be dropped if time is running out

Latest PMP Exam Question No 8

Which of the following are not cost of quality?

Option A : Prevention costs.

Option B : Failure costs.

Option C : Transportation costs.

Option D : Appraisal costs.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Failure costs.

PMI PMP Exam Practice Question No 9

What is a trigger in project risk management?

Option A : An expected situation causing an unidentified risk event to occur.

Option B : A warning sign that an identified risk event might have occurred.

Option C : An unexpected situation causing an identified risk event to occur.

Option D : An unexpected situation causing an unidentified risk event to occur.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

A warning sign that an identified risk event might have occurred.

PMP Certification Exam Agile Question No 10

According to the project plan, a contractor is scheduled to deliver some software components at the end of the day. A regular payment is due to be made to this contractor tomorrow. The project team received a note this morning informing them that the software delivery will be delayed by 2 weeks. This morning, the project team received a note that the software will be delayed by 2 weeks. How should the project management team react?

Option A : The project management team should delay payment for 2 weeks.

Option B : The project management team must immediately find a different contractor.

Option C : The project management team should conduct a meeting with the contractor to resolve the delivery issues before making the payment.

Option D : The project management team should make the payment and reschedule the project plan.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B 

The project management team must immediately find a different contractor.

PMP Latest Edition Mock Test Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply