PMP Exam Preparation Course Test 29 Questions With Answer Keys

Hi PMP aspirants, welcome to AKVTutorials. Looking for a comprehensive set of PMP practice questions that address the nuances of stakeholder engagement and communication management? Engage stakeholders effectively using our practice questions, addressing communication and stakeholder management nuances crucial for PMP success. In this article, you will get PMP Exam Preparation Course Test 29 Questions With Answer Keys. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

During execution in a project to build a major road bridge, your team found a major flaw in the technical drawings. On an ad-hoc base, they had to find and implement a workaround to avoid delays and mitigate technical problems. What should you do next?

Option A : Meticulously document the problem and the workaround to create a requested change to the project management plan, which will then be passed to the body responsible for the change control decision.

Option B : The workaround was performed on a technical level only. As long as it does not influence the function of the bridge or the organizational configuration of the project, a change request will not be necessary. 

Option C : A retroactive formal change request side is not reasonable. Create some additional  documents describing the workaround and sign them by yourself, you can present them during the next regular CCB meeting.

Option D : It is normal in projects that during project execution inconsistencies arise between planning documents and actual implementation. This is no problem as long as the functional status of the product is maintained.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Meticulously document the problem and the workaround to create a requested change to the project management plan, which will then be passed to the body responsible for the change control decision.

PMP Mock Test Question No 2

You recently took over the assignment for a project. The project charter has been developed. What is an appropriate next step for you?

Option A : Develop the risk register.

Option B : Develop the project milestone schedule.

Option C : Develop management plans.

Option D : Get approval for the project management plan.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Develop management plans.

PMP Practice Exam Question No 3

You scheduled a kick-off meeting in order to announce the start of your project, present the plan and develop consensus on it. Another topic will be explanation of each team member’s role. In addition, you planned some time for discussions. You published the agenda of the kick-off meeting some weeks ago to all invited attendees. Now, short term before the event, you receive various cancellations by team members, who say that they cannot join the meeting. But they will be with you when project work will start.

Option A : The kick-off meeting is secondary, you are happy if the team members will do their jobs.

Option B : You should insist on the presence of the team members to the appointed date. 

Option C : If you force team members’ presence, they would anyway be distracted by their current
problems. 

Option D : It is probably a good idea to reschedule the meeting to a day, when all team members can attend.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

You should insist on the presence of the team members to the appointed date. 

PMP Mock Exam Question No 4

During a meeting, a discussion came up: To which degree does your project have to be compliant to the processes enumerated in the PMBOK® .Guide? What should be the guiding principle to answer this question?

Option A : The processes are meant as rough guidelines to which a team should only adhere if there is enough consensus.

Option B : The more processes the project team follows, the better the project’s performance will be.

Option C : The project manager must follow all 49 processes for project management without alterations.

Option D : The project team must select appropriate processes required to meet the project requirements.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

The project team must select appropriate processes required to meet the project requirements.

Project Management Professional Question No 5

Your project team is complaining that the acceptance criteria of their work result are unclear and ask you to provide clarification with the customer. You arrange a meeting, and several criteria are identified. The product acceptance criteria should now be laid down in which documents? (Choose 2)

Option A : Project scope statement

Option B : Work breakdown structure 

Option C : Resource assignments 

Option D : Project scope management plan 

Option E :Can addendum to the project contract

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A, E

Project scope statement , Can addendum to the project contract

PMP Certification Prep Question No 6

During project execution you found out that work is often not performed at the right time and in the right order. Deliverables are made by one team member that cannot be processed by another one. This already leads to timely rework and bad morale among team members. Which project management tool is most appropriate to deal with problems like this?

Option A : Organization chart 

Option B : RACI matrix 

Option C : Communications management plan 

Option D : Work authorization system

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Work authorization system

PMP Exam Question No 7

Your management is applying the 10 percent solution: It has requested that you reduce the budget for the project which you are currently initiating by 10%. What will this probably mean for your project?

Option A : If the budget is cut by 10%, then the project will have an accompanying degradation of quality by 10%.

Option B : If the project budget is an honest one, then a reduction in budget must be accompanied by a trade-off in either time or performance.

Option C : A 10% reduction in budget will be accompanied by a loss of performance much less than the
target reduction in cost. 

Option D : Most projects have “padded” estimates, and the budgetary reduction will force out the padding from the project.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

If the project budget is an honest one, then a reduction in budget must be accompanied by a trade-off in either time or performance.

PMP Exam Sample Question No 8

While applying procurement management processes in your project, you identified the need to gain a more objective understanding of sellers’ capabilities in order to rank proposals and develop a negotiating sequence. Which technique may help avoid bias and subjective decisions best?

Option A : Bidder conference 

Option B : Weighting system 

Option C : Oral contract

Option D : Letter of intent

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Weighting system

PMP Exam Practice Question No 9

During code inspection in a major software development project, a project management team identified frequent occurrences of critical programming errors. These errors are scattered across the code and occur without a discernible pattern. Which tool is most likely to help the team identify areas of error concentration in order to develop a prioritized response strategy?

Option A : Check sheet

Option B : Influence diagram 

Option C : Decision tree 

Option D : Process decision program chart

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Check sheet

PMP Certification Exam Question No 10

The term baseline is used in both disciplines project management and configuration management. Which statement is not true?

Option A : Baselines in system configurations are often also referred to as deltas.

Option B : In configuration management, baselines are used to control change. 

Option C : Project management baselines are used for performance measurement. 

Option D : In project management, baselines help assess variance and trends.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Baselines in system configurations are often also referred to as deltas.

PMP Exam Practice Mock Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply