PMP Sample Test Questions Paper 91 with Explanations

Hi PMP aspirants, welcome to AKVTutorials. Ready to evaluate your understanding of project closure processes with PMP Project Management Professional practice questions? Gain proficiency in various project management methodologies with our practice questions, covering agile, waterfall, and hybrid approaches for comprehensive preparation. In this article, you will get PMP Sample Test Questions Paper 91 with Explanations. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

The first step in WBS creation is

Option A : Determine cost and duration of each project deliverable

Option B : Identify major deliverables of the project

Option C : Identify components of each deliverable of the project

Option D : Determine the key tasks to be performed

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Determine cost and duration of each project deliverable

PMP Mock Test Question No 2

Work package is a

Option A : Element at the lowest level of WBS

Option B : Task with unique identifier

Option C : Required level of reporting

Option D : Task that can be assigned to only one person

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Element at the lowest level of WBS

PMP Practice Exam Question No 3

Going from Level 3 to Level 4 in the work breakdown structure can result in:

Option A : Less estimating accuracy

Option B : Better control of the project

Option C : Lower status reporting costs

Option D : A greater likelihood that something will fall through the cracks

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Better control of the project

PMP Mock Exam Question No 4

A project manager believes that modifying the scope of the project may provide added value
for the customer. The project manager should:

Option A : Change the scope baseline

Option B : Prepare a variance report

Option C : Discuss it in the change control board

Option D : Change the project’s objectives

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Discuss it in the change control board

Project Management Professional Question No 5

 Inspection is used for both Scope Verification and Quality Control. But first deals with — of the work while second deals with — of the product

Option A : Testing, quality

Option B : Correctness, acceptance

Option C : Inspection, testing

Option D : Acceptance, correctness

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Acceptance, correctness

PMP Certification Prep Question No 6

 A Project Charter includes

Option A : Precedence diagramming methods

Option B : Task estimates

Option C : Detailed resource estimates

Option D : The business need for the project

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

The business need for the project

PMP Exam Question No 7

The customer wants to make a major change in the project scope when project is mostly complete. The project manager should.

Option A : Make the change

Option B : Inform the customer of the impact of the change

Option C : Refuse the change

Option D :Complain to management 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Inform the customer of the impact of the change

PMP Exam Sample Question No 8

The key reason to use a WBS is to

Option A : Organize the work

Option B : Prevent work from slipping through the cracks

Option C : Provide a basis for estimating the project

Option D : All of the above

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

All of the above

PMP Exam Practice Question No 9

What does having a project charter do for the project managers?

Option A : Describes the details of what needs to be done

Option B : Describes the names of all team members

Option C : Gives the project manager authority

Option D : Describes the project’s history

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Gives the project manager authority

PMP Certification Exam Question No 10

The subdivision of project deliverables into smaller components is called

Option A : Concept definition

Option B : Flow charting

Option C : Scope definition

Option D : Scope verification

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Scope definition

PMP Latest Edition Mock Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply