PMP Preparation Test Paper 48 Exam Questions

Hi PMP aspirants, welcome to AKVTutorials. Seeking practice questions that assess your understanding of the Project Management Professional Code of Ethics and Professional Conduct? Uphold ethical standards with our PMP practice questions, aligning with the Project Management Professional Code of Ethics and Professional Conduct. In this article, you will get PMP Preparation Test Paper 48 Exam Questions. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Robert is determining the budget that will be required on a project to relocate a company’s operations to a new building. In doing so, he needs to evaluate whether or not funding will be available when expenses need to be paid. What should Robert use in this scenario?

Option A : Funding Limit Reconciliation 

Option B : Historical Information Review

Option C : Financing

Option D : Cost Aggregation

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Funding Limit Reconciliation 

PMP Mock Test Question No 2

A project manager is preparing a communications management plan for a project that includes constructing a new wing in a hospital that will focus on the treatment of cancer patients. Which of the following would not be included in that document?

Option A : The information needs of your stakeholders 

Option B : A description of strategies that will be used to engage those impacted by the project 

Option C : A list of resources that will be allocated to communication activities 

Option D : The process that the project manager or stakeholders can use to escalate concerns

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

A description of strategies that will be used to engage those impacted by the project 

PMP Practice Exam Question No 3

A project to relocate employees of an insurance company to a new office building has been funded and approved. However, the project manager has determined that they will need help from outside vendors to complete it. She also knows that significant changes to scope are likely and a fee will be paid if the vendors meet broad, subjective performance criteria. In this scenario, which type of contract should be utilized?

Option A : Cost Plus Fixed Fee (CFPP) 

Option B : Cost Plus Incentive Fee (CPIF) 

Option C : Cost Plus Award Fee (CPAF)

Option D : Fixed Price Incentive Fee (FPIF)

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Cost Plus Award Fee (CPAF)

PMP Mock Exam Question No 4

Maria is developing the schedule on a project that involves constructing an oil pipeline that will start in Canada and go through the mid-western United States. In order to complete that process, she needs to estimate the minimum project duration and amount of scheduling flexibility. Which tool or technique would accomplish this task?

Option A : Resource Optimization

Option B : Critical Path Method

Option C : Schedule Network Analysis 

Option D : Schedule Compression

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Critical Path Method

Project Management Professional Question No 5

On a project to construct a toll road, which is expected to relieve traffic congestion and generate tax revenue, a team spends time documenting needs of their stakeholders. In this case, what process is being performed?

Option A : Define Scope 

Option B : Plan Scope Management

Option C : Manage Stakeholder Engagement 

Option D : Collect Requirements

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Collect Requirements

PMP Certification Prep Question No 6

A technology company that specializes in creating software applications for dental offices is working on several multi-year projects for their customers. However, three new competitors, who are seeking to take away those customers, have recently entered the market. In this scenario, these marketplace conditions would be best classified as which of the following?

Option A : An enterprise environmental factor 

Option B : An industry standard 

Option C : An organizational process asset

Option D : A lesson that was learned

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

An enterprise environmental factor

PMP Exam Question No 7

A project manager is preparing a procurement management plan for a project that includes renovating a high school on a military base. Which of the following would not be included in that document?

Option A : The currency that will be used to pay vendors working on the project 

Option B : A decision about whether or not certain scope will be completed by the project team or procured from outside vendors

Option C : The timetable of procurement activities 

Option D : A statement on whether or not independent estimates will be needed prior to requesting and purchasing services from vendors

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

A decision about whether or not certain scope will be completed by the project team or procured from outside vendors

PMP Exam Sample Question No 8

As a project manager, you know that your projects are impacted by factors that are often outside of your control. Those factors could be internal or external to your organization, and they could have a positive or negative impact. Enterprise environmental factors are one such example. Which of the following is considered an enterprise environmental factor?

Option A : Political Climate 

Option B : Organizational Communication Requirements

Option C : Human Resource Policies 

Option D : Knowledge Bases

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Political Climate 

PMP Exam Practice Question No 9

A project manager on a factory automation project prepares a memo for the sponsor. It explains that a key deliverable is behind schedule and that the expected completion date will be two weeks later than originally planned. This memo would be classified as which type of project information?

Option A : Work Performance Information 

Option B : Work Performance Data 

Option C : Enterprise Environmental Factors 

Option D : Work Performance Reports

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Work Performance Reports

PMP Certification Exam Question No 10

A project manager at a company that services luxury cars attends a training to learn about earned value management. She believes it could be a valuable tool on her projects. This particular training would be considered a way to strengthen her skills in which of the following areas of the PMI Talent Triangle®?

Option A : Technical Project Management 

Option B : Cost Control 

Option C : Leadership 

Option D : Strategic and Business Management

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Technical Project Management 

Best PMP Exam Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply