PMP Free Exam Questions Test 87 Paper

Hi PMP aspirants, welcome to AKVTutorials. In need of PMP exam preparation resources that include practice questions covering the principles of leadership and team motivation? Achieve integration mastery with our PMP Project Management Professional practice questions, a resource designed to enhance your understanding of this knowledge area. In this article, you will get PMP Project Management Professional Certification Exam Test 87 Questions Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

Should historical information be used during resource planning?

Option A : no, since there is rarely any correlation between resource expectations on one project when compared to another.

Option B : Yes, as historical information is available can provide insight into what type of resources were required on previous projects of similar nature.

Option C : No, since historical information is usually misleading, given the cost of resources have undoubtedly changed since the completion of the prior project.

Option D : .Yes ,since historical information can be easily adjusted to accurately determined current project costs.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Yes, as historical information is available can provide insight into what type of resources were required on previous projects of similar nature.

PMP Mock Test Question No 2

Analogous estimating is a :

Option A : ”bottom-up” estimating technique.

Option B : ”drop-down” estimating technique.

Option C : more costly and more accurately estimating technique.

Option D : technique used when you have no subject matter experts available.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

”drop-down” estimating technique.

PMP Practice Exam Question No 3

Cost estimates:

Option A : are usually presented at a detailed level.

Option B : can be presented in summary of detail.

Option C : are summarized for senior management.

Option D : are provided in detail for senior management.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

can be presented in summary of detail.

PMP Mock Exam Question No 4

In cost monitoring, the s-curve depicts the relation between:

Option A : Schedule completion and time.

Option B : Cumulative value and time.

Option C : Schedule completion and value resources.

Option D : resources and time

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Cumulative value and time.

Project Management Professional Question No 5

In order to produce a cost base line, the project manager requires

Option A : Work packages, work breakdown structure and project schedule

Option B : cost estimates, work breakdown structure and the project schedule.

Option C : cost estimates, work packages `and project schedule.

Option D : cost estimates ,work packages and work breakdown structure

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

cost estimates, work breakdown structure and the project schedule.

PMP Certification Prep Question No 6

Which of the following is an indirect cost?

Option A : Units of Production.

Option B : Lights in the Project War Room

Option C : Tax cost of Salary of project developers.

Option D : Paper purchased by the project.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Units of Production.

PMP Exam Question No 7

Which of the following method is not a depreciation method ?

Option A : Units of production.

Option B : Some of year’s digits

Option C : Declining balance

Option D : Straight line

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Some of year’s digits

PMP Exam Sample Question No 8

An ordered of magnitude estimate is not also known as

Option A : a control estimate.

Option B : a ball park estimate.

Option C : a conceptual estimate

Option D : a preliminary estimate.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

a control estimate.

PMP Exam Practice Question No 9

When the expected cash flow s –curve is above the cost performance base line the project manager should

Option A : investigate the variance to determine if corrective reaction is required.

Option B : bring the situation to the attention of senior management for action.

Option C : adjust the cost baseline to reflect the actual cost to this point.

Option D : do nothing since the project is performing above plan.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

investigate the variance to determine if corrective reaction is required.

PMP Certification Exam Question No 10

Cost estimates may also be expressed in hours days etc. as long as

Option A : it does not result in a misstatement of project cost.

Option B : the program manager agrees.

Option C : the unit of measure is consistent within the project.

Option D : the project manager agrees.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

it does not result in a misstatement of project cost.

PMP Certification Exam Practice Test Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply