PMP Exam Questions Online Test Paper 82 Answer Keys

Hi PMP aspirants, welcome to AKVTutorials. In need of PMP Project Management Professional practice questions that focus on procurement management and contract types? Explore the depths of PMP knowledge using our comprehensive set of Project Management Professional practice questions that reinforce your grasp of the PMBOK Guide. In this article, you will get PMP Exam Questions Online Test Paper 82 Answer Keys. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

The document that describes the project’s scope baseline is: 

Option A : The master schedule 

Option B : The Project Definition document 

Option C : The Scope Paper 

Option D : The Work Breakdown Structure 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

The Work Breakdown Structure 

PMP Mock Test Question No 2

The two closing procedures are called: 

Option A : Contract close out and scope verification

Option B : Contract close out and administrative closure 

Option C : Project closure and product verification 

Option D : Project closure and lessons learned 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Contract close out and administrative closure 

PMP Practice Exam Question No 3

 A work package is: 

Option A : A task on the Work Breakdown Structure 

Option B : A level 1 activity on the Work Breakdown Structure 

Option C : A deliverable at the lowest level of the Work Breakdown Structure 

Option D : An activity on the Project Schedule

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

A deliverable at the lowest level of the Work Breakdown Structure 

PMP Mock Exam Question No 4

A scope change is: 

Option A : Any change to the agreed upon project scope as defined by the approved WBS 

Option B : Market research

Option C : A result of poor planning 

Option D : An output of corrective action

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Any change to the agreed upon project scope as defined by the approved WBS 

Project Management Professional Question No 5

Overall change control requires all of the following except: 

Option A : Maintaining the integrity of the baseline 

Option B : Ensuring that changes to the product scope are reflected in the project scope 

Option C : Coordinating changes across knowledge areas 

Option D : Making process adjustments as a result of deficiencies 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Making process adjustments as a result of deficiencies 

PMP Certification Prep Question No 6

Overall change control is concerned with all of the following except: 

Option A : Determining that a change has occurred 

Option B : Managing changes as they occur 

Option C : Creating change requests 

Option D : Influencing factors that create change to ensure that changes are beneficial 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Influencing factors that create change to ensure that changes are beneficial 

PMP Exam Question No 7

Which of the following is not an input to overall change control? 

Option A : Configuration management system 

Option B : Performance reports 

Option C : Change requests 

Option D : Project plan

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Configuration management system 

PMP Exam Sample Question No 8

Your current project has over 200 specs, 350 engineering drawings and 5500 parts. What tool do you use to apply technical and administrative direction to identify the functional and physical characteristics of items, and control changes to those characteristics? 

Option A : Change control system 

Option B : Configuration management 

Option C : Inventory control 

Option D : Operational definitions 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Configuration management 

PMP Exam Practice Question No 9

Configuration management does all of the following except: 

Option A : Control changes to functional and physical characteristics of an item or a system 

Option B : Record and report changes to any functional and physical characteristics of an item or a system 

Option C : Defines the steps by which official project documents may be changed 

Option D : Audits items and systems to ensure conformance to requirements 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Defines the steps by which official project documents may be changed 

PMP Certification Exam Question No 10

At the outset of a project you should define the processes necessary to account for change. Which of the following is not a standard inclusion in a change control system?

Option A : Performance reports 

Option B : Procedures to handle changes that may be approved without prior review 

Option C : How to handle changes in emergencies 

Option D : The responsibilities of the change control board

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Performance reports 

PMP Practice Test Exam Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply