Hi PMP aspirants, welcome to AKVTutorials. Are you in search of high-quality PMP Project Management Professional practice questions to elevate your exam preparation? Elevate your PMP journey with our comprehensive set of Project Management Professional practice questions, meticulously designed to hone your skills and boost exam confidence. In this article, you will get PMP Project Management Professional Certification Exam Test 1 Questions Answers. PMP (Project Management Professional) is a certification offered by PMI (Project Management Institute) to get a skill managing the people, processes, and business priorities of professional projects. The PMP certification holders are called Project Manager who have proven they have project leadership experience and expertise in any way of working.

PMP Exam Practice Questions

PMP Practice Test Question No 1

A project is experiencing issues that affect the project cost and schedule. What should the project manager use to resolve these issues?

Option A : Cause-and-effect analysis

Option B : Market research

Option C : Earned value management (EVM)

Option D : Schedule crashing

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Cause-and-effect analysis

PMP Mock Test Question No 2

A project manager has concluded the review and approval processes for a project’s key deliverables. The project manager now needs to prepare a report on product quality and project performance for key stakeholders. What should the project manager use to prepare this?

Option A : Quality metrics and project deliverables

Option B : Data analysis and work performance data

Option C : Quality control measurements and work performance information

Option D : Quality inspection reports and the lessons learned repository

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Quality control measurements and work performance information

PMP Practice Exam Question No 3

A project team member decides that engaging the customer on some alternative designs is unnecessary if all functionalities are delivered. The entire team decides to only engage the technical department on the best product design. After user acceptance testing, the customer complains about the selected design. To ensure that the customer accepts the project deliverables, what should the project manager do?

Option A : Update the issue log with the design issue and continue with project execution.

Option B : Ask the customer to accept the project deliverables, as they meet all agreed-upon functional requirements.

Option C : Communicate to the customer that the product design is determined by the technical team.

Option D : Ensure that both the customer and technical team collaboratively select the new product design.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Ensure that both the customer and technical team collaboratively select the new product design

PMP Mock Exam Question No 4

A project is experiencing issues that affect the project cost and schedule. What should the project manager use to resolve these issues?

Option A : Cause-and-effect analysis

Option B : Market research

Option C : Earned value management (EVM)

Option D : Schedule crashing

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Cause-and-effect analysis

Project Management Professional Question No 5

A project status report shows that the earned value (EV) is 24.5, the schedule performance index (SPI) is 0.92, and the cost performance index (CPI) is 1.08. In what area should the project manager implement corrective actions?

Option A : Project cost

Option B : Resource management

Option C : Stakeholder engagement

Option D : Project schedule

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Project schedule

PMP Certification Prep Question No 6

A project manager is working on an assessment project with a tight timeline. What should the project manager do first?

Option A : Develop a data-capturing system.

Option B : Look for lessons learned from previous, similar projects

Option C : Create a questionnaire for assessor proposals.

Option D : Appoint assessors and resources.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Look for lessons learned from previous, similar projects

PMP Exam Question No 7

During a weekly project meeting, a team realizes that a work package is no longer needed. They decide to remove it from the project, and the project manager agrees. What should the project manager do next?

Option A : Inform all stakeholders.

Option B : Update the scope baseline.

Option C : Initiate the change request process.

Option D : Initiate the change request process.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Initiate the change request process.

PMP Exam Sample Question No 8

An issue will cause the project team to miss a critical milestone. The project manager realizes that this issue could have been avoided if the risk had been addressed earlier. What should the project manager do next?

Option A : Hold a meeting with the sponsor and key stakeholders to inform them of the issue.

Option B : Consult with the team and update the project management plan based on their inputs.

Option C : Create and submit a change request that includes a recommendation for corrective action.

Option D : Conduct a meeting to understand the impact of this issue and document the lessons learned.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Conduct a meeting to understand the impact of this issue and document the lessons learned.

PMP Exam Practice Question No 9

During an IT implementation project, the project team is learning about new technology. Adopting some of this new technology will result in reducing the project’s schedule and cost. What should the project manager do?

Option A : Update the project management plan.

Option B : Inform senior management.

Option C : Assign the responsibility to team experts for evaluation of the best use of this technology.

Option D : Require all team members to participate in technology training.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

Assign the responsibility to team experts for evaluation of the best use of this technology.

PMP Certification Exam Question No 10

The project manager discovers that the vendor did not perform software technical testing. Which document confirms whether the vendor should do this testing?

Option A : Product scope description

Option B : Scope management plan

Option C : Procurement management plan

Option D : Statement of work (SOW)

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Statement of work (SOW)

PMP Practice Questions Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply