PMP Certificate Exam Questions Paper 125

Hi PMP aspirants, welcome to AKVTutorials. Seeking a reliable platform for PMP practice questions that focus on risk management, a critical aspect of Project Management Professional certification? Achieve integration mastery with our PMP Project Management Professional practice questions, a resource designed to enhance your understanding of this knowledge area. In this article, you will get PMP Certificate Exam Questions Paper 125. According to the PMI (Project Management Institute), the PMP (Project Management Professional) is an certification examination that is used to determine whether someone has specialized project knowledge, managing skills, and organizing team under project handling to become a project manager. PMP is a globally recognized project management certification that tests a professional’s ability to manage the people, processes, and business priorities of a professional project.

PMP Exam Practice Questions

PMP Exam Prep Practice Test Question No 1

Which of the following statements describes the relationship between project phases and the project life cycle?

Option A : The project lifecycle contains the iterative incremental elements inside a project phase. 

Option B : Collectively, the project phases are known as the project life cycle. 

Option C : The project lifecycle is regarded as a sequence of project activities while phases are defined to control the overlapping of activities. 

Option D : The project lifecycle contains the repetitive elements inside a project phase 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

Collectively, the project phases are known as the project life cycle. 

PMP Exam Preparation Test Question No 2

A project management team discusses what scope means in a project. All of the following statements are true except :

Option A : The processes, tools, and techniques used by project scope management are mostly depending on the application area. 

Option B : Product scope includes features and functions that are to be included in a product or services. 

Option C : Project scope includes the work that must be done in order to deliver a product with the specified features and functions. 

Option D : Project Scope Management includes the processes required to ensure that the project includes all the work required and only the work required. 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

The processes, tools, and techniques used by project scope management are mostly depending on the application area. 

PMP Exam Sample Exam Question No 3

What is the S-curve in project management?

Option A : A graph that is generated if a normal curve is integrated. 

Option B : A graph that is to be integrated to generate a normal curve. 

Option C : A metaphoric description of the short term uncertainties that are present in every project. 

Option D : The graph that describes the typical growth of earned value during the course of the project.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

The graph that describes the typical growth of earned value during the course of the project.

PMP Certification Exam Question No 4

The output of the resource planning process is a document “resource requirements”. This a description of what types of resources are required in what quantities…

Option A : …where the term resources is limited to equipment and materials. 

Option B : ..for each element at the lowest level of the work breakdown structure. 

Option C : …where the term resources is limited to human resources. 

Option D : …to be obtained solely from the performing organization. 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B 

..for each element at the lowest level of the work breakdown structure. 

Free PMP Practice Exam Question No 5

The major output document of Scope definition is the:

Option A : Hierarchically structured WBS. 

Option B : Flat Activity List. 

Option C : Narrative Scope Statement. 

Option D : The Project Charter for the project manager. 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Hierarchically structured WBS.

Best PMP Exam Practice Question No 6

In regards of a cost baseline all of the following is true except :

Option A : It is a time-phased budget that will be used to measure and monitor cost performance on the project. 

Option B : It can be easily created and updated as necessary.

Option C : It is developed by summing estimated costs by period. 

Option D : It is usually displayed in the form of an S-curve.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: B

It can be easily created and updated as necessary. 

Free PMP Exam Prep Question No 7

Which is not true in regard of RoI (Return on Investment)?

Option A : It defines the cumulated net income from an investment at a given point in time or during a defined period. 

Option B : It includes investment, direct and indirect costs and may include allowances for capital cost, depreciation, risk of loss, and/or inflation.

Option C : It is generally stated in currency units, as a percentage or as an index figure. 

Option D : It is the time when cumulated net income is equal to the investment. 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

It is the time when cumulated net income is equal to the investment. 

Latest PMP Exam Question No 8

Regarding Delphi Technique all of the following statements are true except :

Option A : It is a way to reach a consensus of experts. 

Option B : Experts are identified but participate anonymously while a facilitator uses a questionnaire to solicit ideas. 

Option C : The experts are encouraged by the facilitator to make direct contact with each other during the assessment process to create a higher number of feedback loops

Option D : The responses are submitted and are then circulated to the experts for further comment. 

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: C

The experts are encouraged by the facilitator to make direct contact with each other during the assessment process to create a higher number of feedback loops

PMI PMP Exam Practice Question No 9

The responses are submitted and are then circulated to the experts for further comment. The responses are submitted and are then circulated to the experts for further comment.

Option A : Low quality is always a problem; low grade may not be. 

Option B : Grade is a category or rank given to entities having the same functional use but different requirements for quality. 

Option C : Quality is the totality of characteristics of an entity that bear on its ability to satisfy stated or implied needs. 

Option D : Quality can simply be improved through intelligent testing and examining, upgrading requires additional expenses.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: D

Quality can simply be improved through intelligent testing and examining, upgrading requires additional expenses.

PMP Certification Exam Agile Question No 10

Network templates which contain only portions of a network are often referred to

Option A : Subnets or fragnets. 

Option B : Subprojects. 

Option C : Programs. 

Option D : WBS items.

Show/Hide Answer

Answer Keys: YES

Explanation: No

Correct Answer: A

Subnets or fragnets. 

PMP Mock Test Exam Question Bank

Free PMP Exam Complete NotesRita Mulcahy PMP Books Chapters
400+ Short Notes Cards for PMP ExamPMP CAPM Math Formulas PDF
PMP Practice Test: 1PMP Practice Test: 2
PMP Practice Test: 3PMP Practice Test: 4
PMP Practice Test: 5PMP Practice Test: 6
PMP Practice Test: 7PMP Practice Test: 8
PMP Practice Test: 9PMP Practice Test: 10
PMP Practice Test: 11PMP Practice Test: 12
PMP Practice Test: 13PMP Practice Test: 14
PMP Practice Test: 15PMP Practice Test: 16
PMP Practice Test: 17PMP Practice Test: 18
PMP Practice Test: 19PMP Practice Test: 20
PMP Practice Test: 21PMP Practice Test: 22
PMP Practice Test: 23PMP Practice Test: 24
PMP Practice Test: 25PMP Practice Test: 26
PMP Practice Test: 27PMP Practice Test: 28
PMP Practice Test: 29PMP Practice Test: 30
PMP Practice Test: 31PMP Practice Test: 32
PMP Practice Test: 33PMP Practice Test: 34
PMP Practice Test: 35PMP Practice Test: 36
PMP Practice Test: 37PMP Practice Test: 38
PMP Practice Test: 39PMP Practice Test: 40
PMP Practice Test: 41PMP Practice Test: 42
PMP Practice Test: 43PMP Practice Test: 44
PMP Practice Test: 45PMP Practice Test: 46
PMP Practice Test: 47PMP Practice Test: 48
PMP Practice Test: 49PMP Practice Test: 50
PMP Practice Test: 51PMP Practice Test: 52
PMP Practice Test: 53PMP Practice Test: 54
PMP Practice Test: 55PMP Practice Test: 56
PMP Practice Test: 57PMP Practice Test: 58
PMP Practice Test: 59PMP Practice Test: 60
PMP Practice Test: 61PMP Practice Test: 62
PMP Practice Test: 63PMP Practice Test: 64
PMP Practice Test: 65PMP Practice Test: 66
PMP Practice Test: 67PMP Practice Test: 68
PMP Practice Test: 69PMP Practice Test: 70
PMP Practice Test: 71PMP Practice Test: 72
PMP Practice Test: 73PMP Practice Test: 74
PMP Practice Test: 75PMP Practice Test: 76
PMP Practice Test: 77PMP Practice Test: 78
PMP Practice Test: 79PMP Practice Test: 80
PMP Practice Test: 81PMP Practice Test: 82
PMP Practice Test: 83PMP Practice Test: 84
PMP Practice Test: 85PMP Practice Test: 86
PMP Practice Test: 87PMP Practice Test: 88
PMP Practice Test: 89PMP Practice Test: 90
PMP Practice Test: 91PMP Practice Test: 92
PMP Practice Test: 93PMP Practice Test: 94
PMP Practice Test: 95PMP Practice Test: 96
PMP Practice Test: 97PMP Practice Test: 98
PMP Practice Test: 99PMP Practice Test: 100
PMP Practice Test: 101PMP Practice Test: 102
PMP Practice Test: 103PMP Practice Test: 104
PMP Practice Test: 105PMP Practice Test: 106
PMP Practice Test: 107PMP Practice Test: 108
PMP Practice Test: 109PMP Practice Test: 110
PMP Practice Test: 111PMP Practice Test: 112
PMP Practice Test: 113PMP Practice Test: 114
PMP Practice Test: 115PMP Practice Test: 116
PMP Practice Test: 117PMP Practice Test: 118
PMP Practice Test: 119PMP Practice Test: 120
PMP Practice Test: 121PMP Practice Test: 122

Leave a Reply